Remove Group from Project
Hi, Is there a way to remove Project (Project for the web) from a currently linked Group? I can only find a way to remove individuals from group, but cannot move the project out to share to a diffe...
- Nov 18, 2022
Hello mylogi88 ,
Unfortunately there isn't a way to remove the Group once linked to a project. If you want to link this project to another group, one option will be to use the Copy Project feature:
That will create a copy of the current project, with the newly created project, you can link that to the correct group. Then delete the original project if needed?
Paul
Paul_Mather
Nov 18, 2022MVP
Hello mylogi88 ,
Unfortunately there isn't a way to remove the Group once linked to a project. If you want to link this project to another group, one option will be to use the Copy Project feature:
That will create a copy of the current project, with the newly created project, you can link that to the correct group. Then delete the original project if needed?
Paul
Qingfen Lin
Microsoft
Feb 14, 2024Unfortunately, copy project will lose all comment thread, which is the best feature of Project in Teams. It is therefore not possible to reassociate a project with a new group and get connected to a new Team. One would forever stuck in the Teams/Group one has picked in the beginning. A poor design.