Forum Discussion
willard800
Jan 25, 2022Copper Contributor
Remaining work
Good morning. I could use some help getting the REMAINING WORK Detail to show up in my Resource Usage view. when I right-click in the detail area, its not an option and i don't see it listed under ...
willard800
Jan 25, 2022Copper Contributor
So, I know I can add Remaining Work in a Column. But Wanted to know if it can be shown in the Detail table area.
Jan 25, 2022
willard800 --
No, Remaining Work is not a field that you can display in the timephased grid on the right side of the Resource Usage view. Sorry, but hope this helps.
No, Remaining Work is not a field that you can display in the timephased grid on the right side of the Resource Usage view. Sorry, but hope this helps.
- willard800Jan 25, 2022Copper ContributorThanks Dale. appreciate your reply