Remaining Duration
Hi, I have a number of Ghant Charts tracking progress through a large contract whereby there are sometimes around 300 Tasks divided between 8 Teams (resources) each Team starting at the same time an...
Apr 26, 2022
DawkiT --
You can use the Remaining Duration field for the Project Summary Task (Row 0 or Task 0), which will tell you the number of days left in the project. However, you must do the following each reporting period in order for the Remaining Duration column to give you an accurate measurement:
1. Set the Status date to the last day of last week's reporting period (usually last Friday).
2. Manually enter task progress.
3. Reschedule incomplete work from the past into the current reporting period.
Hope this helps.
You can use the Remaining Duration field for the Project Summary Task (Row 0 or Task 0), which will tell you the number of days left in the project. However, you must do the following each reporting period in order for the Remaining Duration column to give you an accurate measurement:
1. Set the Status date to the last day of last week's reporting period (usually last Friday).
2. Manually enter task progress.
3. Reschedule incomplete work from the past into the current reporting period.
Hope this helps.
- DawkiTApr 26, 2022Copper ContributorHi Dale, thanks for your reply, however I'm a bit of a novice and don't really understand this bit. "You can use the Remaining Duration field for the Project Summary Task (Row 0 or Task 0), which will tell you the number of days left in the project"