Forum Discussion
Relation between task duration, start, finish, and predecessors
Well I don't know. Your screen shots only show a partial view of your plan. For example, I can't tell which column is represented by what field (i.e. ID, indicator, etc.). And the screen shot also does not show if the view is sorted or filtered or if the four tasks are the only subtasks under that summary line.
So the bottom line is, there is simply not enough information provided for me (or anyone else) to determine why you are getting what you show in your screen shots.
Just for reference, why would you want to change one of the subtasks to manual scheduling? In my view manual scheduling mode is not very useful except perhaps for creating a very rough starting point for a plan being developed.
John
Hi John-project,
Please see the below screenshot:
I hope this will now give you more information.
Thanks & Regards,
Rohan
- John-projectSep 07, 2021Silver Contributor
Rohan,
Although the latest screen shot does show which fields and that the view is not sorted or filtered, it doesn't show enough to tell me whether there are additional subtasks under the summary.
Are there any resources assigned to the tasks?
If so, do resources have the same base calendar as the Project calendar or if different, how different?
Did you level the plan?
What is the Project calendar?
Are there any task calendars?
Is calculation set for "auto"?
What sequence of steps did you do between the first and second screen shot?
So unfortunately, still not enough information to answer your question. But perhaps the more important issue is, what exactly are you trying to accomplish?
John