Red underline appearing in date column, when updating the plan.
Hi, When updating the project plan, I get red underlying mark in the date column. I need to delete the predecessor, save the file and re-enter the predecessor, after which the plan gets updated. ...
- Aug 16, 2022Robert --
The red squiggly underline tells you that the schedule of that task is incorrect, as defined by the tasks Predecessor relationship. From your screenshot, I can see that the task ID #51 has slipped, which means that task ID #52 and all other Successors need to be rescheduled. I congratulate you for setting dependencies. To resolve your problem, I would recommend that you change every task from Manually Scheduled (the source of your problem) to Auto Scheduled so that Microsoft Project can automatically reschedule tasks whenever needed. Hope this helps.
robertpoddar
Aug 17, 2022Copper Contributor
Hi Dale.
Thank you! 🙂 ...will try it out and let you know..
Thank you! 🙂 ...will try it out and let you know..
robertpoddar
Aug 17, 2022Copper Contributor
Hi Dale
It worked! thank you once again 🙂
It worked! thank you once again 🙂
- Aug 17, 2022Robert --
You are more than welcome for the help, my friend. Please mark my reply as the Best Response, if you would please. Thanks!- robertpoddarAug 17, 2022Copper ContributorDone.. thank you 🙂