Recurring Tasks in MSP

How to set a recurring tasks of frequency more than 1 year? Let us say 18 months frequency of aero engines maintenance

Thank you

  • Ulhas_pmskills,
    For something like that your best option is to do it manually, there is no automated functionality to do anything greater than yearly.
    John

1 Reply

  • John-project's avatar
    John-project
    Silver Contributor
    Ulhas_pmskills,
    For something like that your best option is to do it manually, there is no automated functionality to do anything greater than yearly.
    John