Forum Discussion
Recent changes could not be saved. Refresh the page to undo the changes and continue working
Hello,
Over the past few days I have experienced challenges with the Project for the web part.
It consists of changes not saved in the project folder. Instead, this error message appears.
"Recent changes could not be saved. Refresh the page to undo the changes and continue working. Correlation ID: 6883f5fd-35f0-4bef-8423-8e5bf2dfd36f"
What does this mean and what must be done so that I can use Project for the web again?
Best regards,
3 Replies
- GeorgeB94Copper Contributor
Fix for “Recent changes couldn’t be saved” in Project for the Web / Planner (Schedule Tab)
I finally found the root cause of this issue, and I’m posting it publicly to save others a lot of time.
When you make updates in the Schedule tab in Project for the Web / Planner, the system does NOT run the action under your own user account.
Instead, it executes the updates using the Project/Plan Owner’s security roles and privileges.If the Project/Plan Owner is missing required permissions, the update fails — even if you are a System Administrator.
To fix it, make sure the Project/Plan Owner has at least Read/Write privileges on these Dataverse tables:
msdyn_psserrorlog (PSS Error Log)
msdyn_resourceassignment (Resource Assignment)
msdyn_projectbucket (Project Bucket)
Once those privileges were added, the Schedule tab updates started working immediately.
Hopefully this helps someone else avoid the same debugging nightmare!
- aki1959Copper ContributorIk ervaar hetzelfde probleem, heel storend.
- LASJOHOBrass ContributorThanks for the answer.
I have tried to report the error to our IT department, but they have not yet returned with a solution.
Anyone know how to report it directly to Deleted?