Forum Discussion
Show correct %-Allocation in Resource Usage for a specific project when using Resource Pool
Lets see if this works for you. I didn't use your test files as I already have a couple of my own. I created a master with the two sharer files inserted as subprojects. This is the basic Gantt Chart view:
Then I set up a group for the Resource Usage view. It's a little different from what you have. Note it groups the Project field by assignment
Now, when that group is applied and the Project field is autofiltered for the Sharer1 file, this is the result:
Does that do it for ya?
John
John-project Thanks, this is an option I didn't consider. I tried it but I got the same result for Res1.
Using Assignment for Project and Resource for Name (%-Allocation is empty):
Using Assignment in both cases:
The %-Allocation value is provided for Res1, but the value is wrong, it is not by group.
Would you try with the same sample files I shared just to double check. Thanks!
Please advise, and thanks again for your response!