Scheduling resources in PWA

Hi experts I'm new in PWA with some knowledge of MS project for desktop. I’m trying to schedule some tasks assigning the same resource for all of them. I’m expecting PWA schedule each tasks after a...
  • Dale_HowardMVP's avatar
    May 09, 2023
    Javier1555 --

    I just helped a prospective client with this same problem two weeks ago. Like him, it sounds like your Project Online administrator missed an option when setting up your Project Online instance. Please ask him/her to do the following to fix this problem:

    1. Log into PWA with Administrator permissions.
    2. Navigate to the PWA Settings page.
    3. In the Enterprise Data section of the page, click the Reporting link.
    4. On the Reporting page, select the desired granularity of reporting. I personally recommend the Daily setting.
    5. Click the Save button.

    Once this is done, open and check out your project again, and then click the Publish button. You should now be able to see your resource's utilization in the Capacity Planning page of PWA. Hope this helps.