Forum Discussion

DRogith's avatar
DRogith
Copper Contributor
Oct 07, 2021
Solved

Relation between task duration and project calendar work hours

This is for project on web. I am not able to figure out how the duration filed sets the task end date. As a test, I created project with project calendar working hours: M to F, 5:00 PM - 9:00 PM (4 h...
  • Brian-Smith's avatar
    Brian-Smith
    Oct 22, 2021
    If you have Project Plan 1,3 or 5 licenses then Project for the web is definitely NOT out of scope for support. You should be able to open a new case via the Microsoft 365 Admin center (or your admin should). If you tried this before - ping me the case number to brian.smith@microsoft.com and I will find out why you were told this. Best regards, and apologies for the delay in responding - just back from vacation, Brian.

Resources