Forum Discussion
Railway construction km Filter
- Jul 24, 2023
This is what I get when I create a filter based on the Date Range filter. Does it not do what you want?
John
This is what I get when I create a filter based on the Date Range filter. Does it not do what you want?
John
I have crated the same Filter, and when I apply it to the range of KM 6 and KM7 than only Task 2 appears.
But what I need is that all 4 activities needs to appear, because they have workload in this km range.
Do you have any Idea?
- Ignacio_MartinJul 25, 2023Steel Contributor
Hello ThomasvP
The filter that John describes works correctly
You can add it to ask the interval of kilometers as indicated in the attached video.
Regards
- ThomasvPJul 25, 2023Copper Contributor
Hey both, thanks so much. now it is working.
(I mixed up start and finish before)
- John-projectJul 25, 2023Silver Contributor
Yeah, I thought maybe that was the problem. I'm glad you got it working and thanks for the feedback.
If I answered your question, please consider marking my response as the answer.
John