Re: PWA is no longer creating connected SharePoint site when new project is added/ Groups not added

Hello Malloy993950 ,

Do you see any errors in the Manage Queue page in PWA settings? Is the EPT using the default Project Site template or are you using a custom site template?

Paul

5 Replies

  • Malloy993950's avatar
    Malloy993950
    Copper Contributor

    Paul_Mather 

    Sorry for the delay on this one. Yes I see two error messages for each project created. I have attached screenshots of each error message. 

    Thank you, 

     

    Malloy993950

    • Paul_Mather's avatar
      Paul_Mather
      MVP

      Hello Malloy993950 ,

      You've hit a SharePoint limit on the view threshold, this is 5000 items. I'm not sure how or why that limit is being hit when creating a site. Do you have lots of projects / groups on that site collection? It's probably worth opening support ticket with Microsoft via your M365 tenant - you're M365 admin will be able to do you (if you've not got the correct access).

      Paul

      • Malloy993950's avatar
        Malloy993950
        Copper Contributor
        We have about 2450 Projects in PWA.
        I have created a project with the default site template with standard enterprise project type and we got the same errors.

        Any suggestions?