Brett --
If I had a dollar for every time I have seen that error dialog, I would be retired by now. I even got that error dialog during a live webinar where I was presenting how to use the Excel Visual Reports feature in Microsoft Project. Totally embarassing! In that webinar, I tried a second time, and got the error dialog again. Fortunately, I had saved a copy of the Excel file with the exported Excel Visual Report, so I simply opened the Excel file and continued with the webinar.
The truth is that the error message you are seeing is quite common in Microsoft Project. I suspect there is some kind of bug that causes the message to appear intermittently, but Microsoft has never admitted this is a bug, and thus, has never fixed it.
So, you and your PMs are not doing anything wrong. What I have done in the past is to keep exporting the Excel Visual Report until I get no error message. That's the only workaround I have discovered with this annoying "feature" in Microsoft Project. Hope this helps.