Re: Project Professional 2016 and Project Online fields

Hello junaidzia ,

When using Project Online, custom fields are created via PWA Settings > Enterprise Custom Fields and Lookup Tables. Here is a guide: https://pwmather.wordpress.com/2014/01/17/getting-started-with-projectonline-part-2-ps2013-office365-project-ppm-sharepointonline-pm/ 

For a full overview, this might help: https://pwmather.wordpress.com/2014/07/22/getting-started-with-projectonline-round-up-ps2013-office365-project-ppm-sharepointonline-pm-sp2013/ 

Some of the screens might have changed slightly such as where you set the permission mode but the majority of these articles will still be correct.

Paul 