Forum Discussion
Project Online tasks not available in task tab
Hi Dale,
I am also having this issue. I have done what you have mentioned here and all my tasks are published. I still cannot see any thing in Tasks section. I am also the owner of the PWA.
Svashisht2023 Dale_HowardMVP Were you ever able to get to the bottom of this? I am having the same problem. tasks are showing up both in project desktop and in the resources tab of Project online, but when I go to the specific tasks tab on project online they do not show up. Any assistance would be much appreciated.
- Svashisht2023Aug 02, 2024Copper Contributor
_isaac136 what worked for me was the manner in which the resources were created in Resource center. It all worked for me when I created the resources using these 2 options (highlighted in image below):
let me know if it works for you. hope it helps. Cheers.