Forum Discussion
Project Online tasks not available in task tab
Your screenshot is of the Resource Center page. You need to click the Tasks tab to display the Tasks page in PWA. You should see your assigned tasks there. Let us know what you find.
- RodFrommNov 14, 2023Steel Contributor
emilesteenkamp1750 Try this.
- Go to PWA and open the project in MS Project Desktop
- Select View, Resource Sheet
- Does it show the Local Resource icon next to all of the resources?
If it does, that means you manually assigned resources to tasks that are not in your enterprise resource pool and they will not show up in timesheets. If this is the case, I would create a new project and populate the Build Team in the PWA.
- Jefferson_XuNov 14, 2023Copper Contributor
I have a same issue as yours. Did you find solution eventually? Thank you!emilesteenkamp1750
- Jun 20, 2023Emile --
One final idea for you. Open and check out the project. Apply the Gantt Chart view. Right-click on the Duration column header and select the Insert Column item on the shortcut menu. In the list of available Task fields, select the Publish column. Is the Publish value for every task set to Yes? If not, change the Publish values to Yes and then republish the project. Hope this helps.- Svashisht2023Mar 22, 2024Copper Contributor
Hi Dale,
I am also having this issue. I have done what you have mentioned here and all my tasks are published. I still cannot see any thing in Tasks section. I am also the owner of the PWA.- _isaac136Jul 31, 2024Copper Contributor
Svashisht2023 Dale_HowardMVP Were you ever able to get to the bottom of this? I am having the same problem. tasks are showing up both in project desktop and in the resources tab of Project online, but when I go to the specific tasks tab on project online they do not show up. Any assistance would be much appreciated.