Forum Discussion
emilesteenkamp1750
Jun 14, 2023Copper Contributor
Project Online tasks not available in task tab
I'm trying to setup a test project and setup the following tasks in Project desktop. I've successfully connected Project desktop with PWA but the issue is that the tasks in Desktop is not availab...
Jun 16, 2023
Emile --
Display the Build Team dialog. In the list of resources in the lower-right corner of the dialog, make sure that your Booking value is set to Committed. If not, specify this value, and then publish the project again. Hope this helps.
Display the Build Team dialog. In the list of resources in the lower-right corner of the dialog, make sure that your Booking value is set to Committed. If not, specify this value, and then publish the project again. Hope this helps.
emilesteenkamp1750
Jun 19, 2023Copper Contributor
- Jun 19, 2023Emile --
Your screenshot is of the Resource Center page. You need to click the Tasks tab to display the Tasks page in PWA. You should see your assigned tasks there. Let us know what you find.- emilesteenkamp1750Jun 19, 2023Copper Contributor
- RodFrommNov 14, 2023Steel Contributor
emilesteenkamp1750 Try this.
- Go to PWA and open the project in MS Project Desktop
- Select View, Resource Sheet
- Does it show the Local Resource icon next to all of the resources?
If it does, that means you manually assigned resources to tasks that are not in your enterprise resource pool and they will not show up in timesheets. If this is the case, I would create a new project and populate the Build Team in the PWA.