Forum Discussion
Project Online 'Submit' button is greyed out and the workflow is stuck at processing stage.
Hello Paul_Mather
Thank you for the information. I am checking with IT when the Microsoft 365 tenant was created. I think it has been created for a few years ago, but definitely Project Online site was just created early this month. Is the retirement timeline applied to Microsoft 365 tenant or Project Online site?
If I use Power Automate, is it connected to PWA and the Workflow Stage Status still shows tracking of the workflow?
Since my project has not reserved budget for Power Automate license cost, is there any other solution than Power Automate?
Hello Arintra ,
The retirement is at the M365 tenant level. I'd confirm with It when the M365 tenant was created.
Regarding alternative solutions, it depends on your requirements. Power Automate is not a direct replacement for the built in workflows in Project Online either, it does not have the same capability when it comes to Project Online. Here is a post Using Power Automate for Project Lifecycle Workflows in Project Online – Part 1 | Microsoft Community Hub
Paul
- ArintraMay 25, 2025Copper Contributor
Hello Paul_Mather ,
One more question regarding Power Automate license, I just found that the account that I use for setting up Project Online has Power Automate app included. After I check this account's license, it shows that this account includes Power Automate for Project and Power Automate Free, though only Project Plan 3 license is assigned to this account.
Does this mean Power Automate for Project license is already bundled to Project Plan 3 license, it's no need to pay more for Power Automate license if the feature required for Project is just standard project workflow?Please advise.
- Paul_MatherMay 27, 2025MVP
Hello Arintra ,
It depends what you need to build in Power Automate, you might find that the license you have is enough. If you need any of the Premium connectors, you will have to pay for a new license. You'll see when you start to use Power Automate what is available to you.
Paul
- ArintraMay 24, 2025Copper Contributor
Hello Paul_Mather ,
Thank you so much for the help. The provided information has clarified what happens with my site. Seems like I need to learn Power Automate, so I can configure Project Online to make it works as user's request.
Appreciated your help!
Arintra