Forum Discussion
James_Price
Dec 11, 2023Brass Contributor
POL: Problem with changing a SP Designer workflow...
Hi Team, In POL, I created a project without workflows. I then created a simple workflow using SPD and then updated the EPT with the new workflow name. But when open a project of that EPT I get an...
RodFromm
Dec 13, 2023Iron Contributor
Does the new workflow work correctly if you create a new project? If it does, it will probably be faster to just recreate the project than try to resolve a one-time workflow issue.
James_Price
Dec 13, 2023Brass Contributor
Many thanks RodFromm
The new workflow works fine. The problem is that there are about 50 existing projects that need this workflow applied to them.