New Enterprise Project Types not showing in New Project Ribbon
I am creating new Enterprise Project Types in Project Online. I have setup site and plan templates to be included with them. After saving them they are showing in the Enterprise Project type list in ...
- May 16, 2023Jedihercules --
If you specified a Department value for the EPT, then only people with that value specified in their Resource Departments field will be able to see the EPT. Does that help? Let us know.
Jay_Dee
Feb 02, 2025Copper Contributor
Hello, I have created Enterprise Project Types and created Project templates that have been uploaded as "templates" however in the drop-down menu, "None" is showing up (as per the image). Could you please advise whether I have missing something in terms of the setup? Thank you.
Feb 03, 2025
Jay_Dee --
To save your projects as "templates" did you complete the following steps:
- Launch Microsoft Project desktop and connect to Project Online.
- Open the file you want to save as an enterprise template.
- Click File > Save As.
- In the Project Web App section of the page, click the large Save button.
- In the Save to Project Web App dialog, enter a name for the project.
- In this dialog, click the Type pick list and select the Template item.
- Click the Save button.
- In the Save as Template dialog, select all of the checkbox options and then click the Save button.
- Click the File tab and then click the Close button.
- In the Backstage, click the New tab and then click the Enterprise tab near the top of the page.
In the Enterprise section of the New page, you should see the new enterprise template which you just saved. These are the steps required to save a project as an enterprise template. There is no other method for doing this. So, did you complete the preceding steps? Let us know and we will try to help you.