Forum Discussion
MaxiButler
Jan 26, 2022Copper Contributor
MS Projects | Progress line moves back when printed
Hi, This has happened randomly to a couple of people at work over the last week. The progress line on the project is in the correct place when looking at the workspace, but when we go to print th...
Chris_Hill
Jan 28, 2022Copper Contributor
Thanks for the reply. How do you raise a ticket with Microsoft support?
Trutz_Stephani
Jan 28, 2022Steel Contributor
You should talk to your IT department, i.e. the administrator of your Microsoft tenant. The can do that via the admin portal.
- GabrielMaury1Feb 18, 2022Copper Contributor
- Chris_HillFeb 18, 2022Copper Contributor
Hi
Yes. I got our IT team to raise it with Microsoft. It appears a recent update introduced the error. They ended up having to revert mine to a previous version. They then changed my automatic update interval to 6 monthly, in the hope that they will have resolved the issue by the time my next scheduled update is due.