Forum Discussion
IlyaAdadurov
Jul 07, 2022Copper Contributor
MS Project tasks progress approval for Project Manager does not work
Hi all! I am setting up Project Onilne in my organization, unfortunatelly we don't have experienced professional in Project Server settings, and it looks quite tricky for me to understand all of the...
- Jul 07, 2022Илья, необходимо создать задачу в WEB под другим пользователем и опубликовать проект.
После публикации в выпадающем списке кроме Вас появится и этот человек.
Тот кто будет утверждать задачи в этом проекте должен хотя-бы один раз создать и опубликовать хоть одну задачу, далее его можно будет выбрать утверждающим в других:)
Vasily_Zaytsev
Jul 07, 2022Iron Contributor
In Russian it is "Управляющий назначением"
IlyaAdadurov
Jul 07, 2022Copper Contributor
One more step forward, thanks a lot!
Got it, but there is only me in the drop-down list and I can't put another name in the cell.
Is there a place where the list of "Status Managers" is created? Is it inside particular Project or is it set on Server?
Got it, but there is only me in the drop-down list and I can't put another name in the cell.
Is there a place where the list of "Status Managers" is created? Is it inside particular Project or is it set on Server?
- Jul 07, 2022Ilya --
The project manager of the project in question must open and check out the project. Then he must insert the Status Manager column, and select his own name for every detailed task in the project. Then the project manager must save and publish the project. There is no way for YOU to set the Status Manager to someone else. It must be done by the current project manager. Hope this helps.- IlyaAdadurovJul 08, 2022Copper ContributorDear Dale!
Thanks for you comment.
I'll translate answer of Vasily above to English, it gives to clear process to get new name in column "Status Manager":
To have his name in "Status Manager" column, new Project Manager must:
- check out project
- add at least on task by himself in Project Plan (online or in Project Desktop), task may be temporary and may be deleted later
- save plan to server
- publish project
- check-in project
After that you'll have name of the person who added task in the drop-down list of cells of "Status Manager" column.
- Vasily_ZaytsevJul 07, 2022Iron ContributorИлья, необходимо создать задачу в WEB под другим пользователем и опубликовать проект.
После публикации в выпадающем списке кроме Вас появится и этот человек.
Тот кто будет утверждать задачи в этом проекте должен хотя-бы один раз создать и опубликовать хоть одну задачу, далее его можно будет выбрать утверждающим в других:)