Forum Discussion
NaomiBrill
Oct 19, 2023Brass Contributor
Link subprojects to master project if you don't have a network drive
Hey we have a master project with a resource pool which is shared with individual plans/subprojects. However, we are not able to link the subprojects to the master project on SharePoint and we don't ...
Oct 20, 2023
NaomiBrill --
Are you using Project for the Web (project.microsoft.com) or are you using Project Online (companyname.sharepoint.com/sites/pwa)? Which URL do you see when you access web app?
Are you using Project for the Web (project.microsoft.com) or are you using Project Online (companyname.sharepoint.com/sites/pwa)? Which URL do you see when you access web app?
NaomiBrill
Oct 23, 2023Brass Contributor
Hi Dale,
I've just been given access to Project Online! Will I be able to upload our existing plans that we created using the desktop app?
Many thanks,
Naomi
I've just been given access to Project Online! Will I be able to upload our existing plans that we created using the desktop app?
Many thanks,
Naomi
- NaomiBrillOct 30, 2023Brass ContributorThanks so much for your help so far. I think I'm at the point now where I've got everything I need up and running, but will definitely keep you in mind if we require any further support.
- Oct 26, 2023Naomi --
The first thing you need to do is to create your Project Online login account in Microsoft Project. To do this, complete the following steps:
1. Click Microsoft Project and then open a new blank project, if needed.
2. Click File > Info > Manage Accounts.
3. Click the Add... button in the Project Web App Accounts dialog.
4. Enter a friendly name in the Account Name field, enter the URL of your Project Web App in the Project Server URL field, leave the "Set as default account" checkbox selected, and then click the OK button.
5. In the lower left corner of the Project Web App Accounts dialog, select the Choose An Account option, and then click the OK button.
6. Exit Microsoft Project completely and then relaunch the software.
7. In the Login dialog, click the OK button to connect Microsoft Project to Project Online.
From your description, it sounds like your enterprise Standard calendar is stuck in a Checked Out state. To force check it in, do the following:
1. Launch your preferred web browser and navigate to the Home page of PWA.
2. In the upper right corner of the page, click the Settings menu button (it looks like a gear wheel) and then select the PWA Settings item.
3. In the upper right corner of the PWA Settings page, click the "Force check in enterprise objects" link.
4. At the top of the page, click the pick list and select the Enterprise Calendars item.
5. Select the enterprise Standard calendar and then click the Check In button.
Once the enterprise Standard calendar is checked in, return to the PWA Settings page and click the Enterprise Calendars link at the top of the page. On the Enterprise Calendars page, select the Standard calendar and then click the Edit button. This action will launch Microsoft Project, connect it to Project Online, and then open the enterprise Standard calendar for editing. You will need to add all of your company's holidays as nonworking time for at least 5 years or so.
Also, the answer is "Yes" to the question about the "Allow master projects to be saved and published" option needing to be selected so that you can save your master project.
Naomi, if you need professional help with setting up and using Project Online in your organization, I would be grateful if you would allow me to compete for your business. I think I have already proven my skills and knowledge to you on this thread. Hope this helps. - NaomiBrillOct 26, 2023Brass ContributorHi Dale,
Thank you so much for your support. I really appreciate it!
I have been working with our IT support team who unfortunately are not able to help much as they do not have expertise in Project, even after doing a fair amount of research online. I however have managed to set up the Enterprise Resource Pool, but having problems with the Enterprise/Standard Calendar. I somehow managed to add one exception, but can't edit it anymore. It's saying it has been checked out but I can't work out how to uncheck it or edit it. Do you have any ideas?
Also you said in order for us to save existing desktop projects into the online version, we have to make sure to allow this permission in the Additional server settings - can you confirm if this is the checkbox "Allow master projects to be saved and published"? Does anything else have to be checked?
How do I create my PWA login account?
Any further support you could provide regarding setting up the Enterprise calendar and converting the projects created in the desktop app to the online app would be incredibly helpful.
Thanks, Naomi - Oct 23, 2023Naomi --
Yes, but confirm the following:
1. Your Project Online app admin has added you to the Project Managers security group.
2. Your app admin has populated the Enterprise Resource Pool with names of the project managers and team members in your organization.
3. Your app admin has changed the default permission to allow you to save master projects in Project Online. It's in the Additional Server Settings dialog.
4. In Microsoft Project you have created your PWA Login account, then exit Microsoft Project.
5. Launch Microsoft Project and connect to PWA.
Once you have done this, you can open each of your MPP files, click File > Save As, and save them in Project Online. You can also build your project team in each subproject with enterprise resources from the Enterprise Resource Pool.
Hope this helps.