Link Procurement Tasks to deliver Just-In-Time without using up slack?
In MS Project, what is the recommended way to link procurement tasks such that the duration is the lead time of the material, the task "finishes" (material delivers) when needed by the subsequent tas...
TrevorATperfectproject
Dec 23, 2025Brass Contributor
Brett,
this is how to make an "intended start" halfway along the total float (slack).
You can adjust the formula to drop the intended start anywhere between earliest and latest starts.
Example of custom fields, custom table, custom view.
Any help?
TrevorATperfectproject
Dec 27, 2025Brass Contributor