Hours v Days - A little advice required on managing multiple projects concurrently
- Mar 18, 2022
Tony_Platts,
Sounds like a perfect application for a fixed duration task. In your example, set the fixed duration to 3 days and set the work to 3 hours. When you assign a resource at 100% Project will linearly spread the 3 hours over the 3 day period. Whether the resource actually works 1 hour each day or 3 hours on any of the 3 days doesn't matter, you've captured the intent.You may also find this thread and discussion helpful:
https://techcommunity.microsoft.com/t5/project/fixed-duration-task-effort-driven-why-is-the-3rd-resource-set-at/m-p/3256500
Hope this helps.
John
Hopefully this example will answer your latest questions. I first set the task type, then the duration, then the work, and then assigned the resource "Joe" at 100%. Doing so let's Project calculate the actual assignment level to meet the duration and work values (i.e. 13%). This is the result in the Task Usage view.
John
- John-projectMar 22, 2022Silver ContributorTony_Platts,
You're welcome and thanks for the feedback.
John