Re: Help needed on MS Projects.

John-project 

Thank You so much for your explanation. Do you perhaps know of a formula I can use just for testing purposes? 

3 Replies

  • John-project's avatar
    John-project
    Silver Contributor

    Marius350 

    Here is a sample plan with a group of milestones under a summary line. The Number1 field is customized with the formula shown. The summary line is set to sum up the number of completed milestones.

    Hope this helps.

    John

     

    • Marius350's avatar
      Marius350
      Copper Contributor

      John-project Thank You so much. I have tried the formula on myside but it still give me a syntax error. I also tried to retype it again but it still give me a syntax error.

       

      Can you please assist?

      • John-project's avatar
        John-project
        Silver Contributor

        Marius350 

        I would help if you would post your formula. However, it may be as simple as changing the delimiter, which is a comma on my system, with a semicolon, which may be the delimiter on your system. For example, try this syntax:

        IIf([Milestone]=True And [% complete]=100;1;0)

         

        John