Getting #ERROR in Custom Text Field Using IIf Function For The False Argument
- Aug 31, 2022
John,
In the digital world dates are represented by numbers. For example, 8/29/22 12:00 PM is stored as 44802.54. String based fields (e.g. Text1) can of course have any string variable (e.g. "NA").
What I don't fully understand is that the latest date possible with Project (current versions) is 12/31/2149 which is represented by: 91312.34, yet using the ">50000" trick still works for "NA".Interestingly enough, an "if" statement in VBA can directly detect "NA" in a date field. For example, the following code works fine:
Sub testNA()
For Each t In ActiveProject.Tasks
t.Text1 = "yes"
If (t.BaselineStart = "NA") Then t.Text1 = "no"
Next t
End Sub
Oh the mysteries of Project 🙂
John
Are you sure that works, because it doesn't for me. Something is fishy about your formula anyway because you show the false result to be a null string (i.e. not a numerical value) which is not valid for a number field. Here's what I get (substituting a 1 for your KPI number).
John
John-project All I know is I'm not getting an error. Below is the custom field and formula, and what the view looks like. Now if I do hover over the graphical indicator Cost KPI field. For tasks where the Actual Start=NA, it does display #ERROR, but only when I hover over it. Otherwise it just shows as blank.