Forum Discussion
Getting #ERROR in Custom Text Field Using IIf Function For The False Argument
- Aug 31, 2022
John,
In the digital world dates are represented by numbers. For example, 8/29/22 12:00 PM is stored as 44802.54. String based fields (e.g. Text1) can of course have any string variable (e.g. "NA").
What I don't fully understand is that the latest date possible with Project (current versions) is 12/31/2149 which is represented by: 91312.34, yet using the ">50000" trick still works for "NA".Interestingly enough, an "if" statement in VBA can directly detect "NA" in a date field. For example, the following code works fine:
Sub testNA()
For Each t In ActiveProject.Tasks
t.Text1 = "yes"
If (t.BaselineStart = "NA") Then t.Text1 = "no"
Next t
End Sub
Oh the mysteries of Project 🙂
John
Another way to handle it is:
Text1=IIf([Baseline Start]=projDateValue("NA"),"no","yes")
John
John-project Any idea why Project would store a numerical value for the baseline start date field instead of the value that actually displays "NA". Thats a little strange. Also I think there were other customer fields I have that evaluate whether a date field has "NA", and those didn't produce errors, but they were also different custom field types so maybe that had something to do with why the formulas worked.
- John-projectAug 31, 2022Silver Contributor
John,
In the digital world dates are represented by numbers. For example, 8/29/22 12:00 PM is stored as 44802.54. String based fields (e.g. Text1) can of course have any string variable (e.g. "NA").
What I don't fully understand is that the latest date possible with Project (current versions) is 12/31/2149 which is represented by: 91312.34, yet using the ">50000" trick still works for "NA".Interestingly enough, an "if" statement in VBA can directly detect "NA" in a date field. For example, the following code works fine:
Sub testNA()
For Each t In ActiveProject.Tasks
t.Text1 = "yes"
If (t.BaselineStart = "NA") Then t.Text1 = "no"
Next t
End Sub
Oh the mysteries of Project 🙂
John- JBLT-77Aug 31, 2022Iron Contributor
John-project Would possibly using a different custom field type than a Text field be better to produce a Yes/No value based on whether a date field contains "NA". It appears to work for number custom field types, but that field type can't produce a Yes/No Value. I played around with the flag custom field type and I don't think that will work either.
- John-projectAug 31, 2022Silver ContributorJohn,
What makes you think it works for a custom Number field? It still generates an error if the test value equals "NA".
Why not just use the "tricks" I showed you. There are a few things that defy normal logic thinking when working with formulas in Project custom fields so the goal is to find a workaround and use it.
John