Forum Discussion
JonathanGlaser
Nov 08, 2022Copper Contributor
Creating a customized column to show the four predecessor task types
I would like to insert a column that shows which of the four (4) possible predecessor task types (FS, SS, FF, SF) all the tasks have. Can anyone tell me if this is even possible, and if so, how can ...
- Nov 10, 2022Jonathan,
Okay, then this formula should do it. Note, after posting my first response I realized it was not the Mid function but the Instr function that is needed.
Text1=IIf([Predecessors]<>"",Switch(instr(1,[Predecessors],"S")=0 And instr(1,[Predecessors],"F")=0,"FS",InStr(1,[Predecessors],"SS")>0,"SS",instr(1,[Predecessors],"FF")>0,"FF",instr(1,[Predecessors],"SF")>0,"SF",instr(1,[Predecessors],"FS")>0,"FS"),"")
John
John-project
Nov 10, 2022Silver Contributor
Jonathan,
Okay, then this formula should do it. Note, after posting my first response I realized it was not the Mid function but the Instr function that is needed.
Text1=IIf([Predecessors]<>"",Switch(instr(1,[Predecessors],"S")=0 And instr(1,[Predecessors],"F")=0,"FS",InStr(1,[Predecessors],"SS")>0,"SS",instr(1,[Predecessors],"FF")>0,"FF",instr(1,[Predecessors],"SF")>0,"SF",instr(1,[Predecessors],"FS")>0,"FS"),"")
John
Okay, then this formula should do it. Note, after posting my first response I realized it was not the Mid function but the Instr function that is needed.
Text1=IIf([Predecessors]<>"",Switch(instr(1,[Predecessors],"S")=0 And instr(1,[Predecessors],"F")=0,"FS",InStr(1,[Predecessors],"SS")>0,"SS",instr(1,[Predecessors],"FF")>0,"FF",instr(1,[Predecessors],"SF")>0,"SF",instr(1,[Predecessors],"FS")>0,"FS"),"")
John
JonathanGlaser
Nov 11, 2022Copper Contributor
Hi John
Thank you so much!
While I have some basic understanding of formula functionality, this one you provided introduced me to a function I'm unfamiliar with. It's been a valuable learning experience.
Could you perhaps point me to any helpful resource(s) where I can acquire further understanding specifically of formulae?
Kind regards
Jonathan
Thank you so much!
While I have some basic understanding of formula functionality, this one you provided introduced me to a function I'm unfamiliar with. It's been a valuable learning experience.
Could you perhaps point me to any helpful resource(s) where I can acquire further understanding specifically of formulae?
Kind regards
Jonathan
- John-projectNov 11, 2022Silver ContributorJonathan,
You're welcome and thanks for the feedback.
I work a fair amount with VBA (Visual Basic for Applications) in Project and there is a lot of cross-over for custom field formulas. As far as a helpful resource, click on the Help tab on the Project ribbon and when the Help pane pops up just type in "custom field formulas". You can also contact my colleague Ismet Kocaman (just Google him), who has articles and publications on custom field formulas for Project. I'm sure there are also other books or help articles available on the internet but I can't cite any specific links.
John