Forum Discussion

JonathanGlaser's avatar
JonathanGlaser
Copper Contributor
Nov 08, 2022
Solved

Creating a customized column to show the four predecessor task types

I would like to insert a column that shows which of the four (4) possible predecessor task types (FS, SS, FF, SF) all the tasks have. Can anyone tell me if this is even possible, and if so, how can ...
  • John-project's avatar
    John-project
    Nov 10, 2022
    Jonathan,
    Okay, then this formula should do it. Note, after posting my first response I realized it was not the Mid function but the Instr function that is needed.
    Text1=IIf([Predecessors]<>"",Switch(instr(1,[Predecessors],"S")=0 And instr(1,[Predecessors],"F")=0,"FS",InStr(1,[Predecessors],"SS")>0,"SS",instr(1,[Predecessors],"FF")>0,"FF",instr(1,[Predecessors],"SF")>0,"SF",instr(1,[Predecessors],"FS")>0,"FS"),"")

    John