Forum Discussion
Correlation ID in project for the web
kblarsen Can you provide a screenshot of what you are doing, because it is possible to create new calendar templates and assign them to projects and resources.
Here is an article with additional information Create and apply a work calendar in Project for the web - Project for the web | Microsoft Learn
RodFromm Hi,
I am trying to do what you and the article are writting.
Have created a new template calendar as shown below:
When I try to select and use it in a project I get:
/PC, Kim
- RodFrommFeb 26, 2024Iron Contributor
kblarsen That error message is related to a bug, which I submitted to Microsoft. Currently if a project was created in Project Accelerator is opened from the Project Home page you have access to Calendar Setting that are not available in the Project Accelerator. This can be very confusing. They are working on fixing this issue so the Calendar options are the same whether you are in the Accelerator, or open the project from the Project Home page..
To assign a different calendar to a project, go to your Project Accelerator, open the project then go to the Summary form and assign the new Calendar template as shown below- kblarsenMar 01, 2024Copper Contributor
RodFromm Thanks for information.
Have tried that and can change the template, but in the project I cannot see any effekt in project plan.
The non-workdays set in teh template are still used as workdays
The sss task is plan in a non-working day periode.
/Kim
- RodFrommMar 01, 2024Iron Contributor
kblarsen Compare the assigned project calendars, to the calendar assigned to the resources on your project? If they are different that could be the issue. Also remember when you assign a calendar to a project or resource it applies a copy of the calendar. If you later change the calendar you have to remove and reapply it for the changes to be applied (it's not dynamic).