Forum Discussion
Copy and paste to a PfW schedule...
- Nov 13, 2023
Hey James_Price ,
I don't see this issue. If the Name cell has the green outline so it just selected (no cursor flashing inside it for typing), copying and pasting multiple task names from multiple rows in Excel works fine. If I click in the Name cell to make it active to type with the cursor flashing, the values from multiple rows will just create 1 new task.
Paul
Hi James_Price ,
I don't see that message / issue. Where are you copying from? I'll try to repro if you can provide exact steps / details of the source data.
Paul
Sorry for the delay on this but I thought I'd replied last week... d'oh. So what I've been doing:
1. I copy a range from Excel (A1:A3 with values a, b and c).
2. In the Project Task tab, I select Grid and click on the 'Add new task'. This changes to a green outlined cell with 'Name' inside it.
3. When I paste, a black on white text pop up says 'The paste option is not supported'.
4. If I click again in the cell, I get the cursor key and this only pastes 'a b c' in the cell.
Hope this helps
Many thanks
- Paul_MatherNov 13, 2023MVP
Hey James_Price ,
I don't see this issue. If the Name cell has the green outline so it just selected (no cursor flashing inside it for typing), copying and pasting multiple task names from multiple rows in Excel works fine. If I click in the Name cell to make it active to type with the cursor flashing, the values from multiple rows will just create 1 new task.
Paul
- James_PriceDec 11, 2023Brass ContributorHi Paul and Dale,
FYI it appears that you can't copy and paste into the Grid view via PowerApps. Is that your understanding/experience?
Many thanks
James- Paul_MatherDec 12, 2023MVP
Thanks for the update James_Price ,
That makes sense why I couldn't repro the issue you were seeing, I was not using the Power App UI. It's a shame copy and paste doesn't work in the Power App UI.
Paul
- James_PriceNov 13, 2023Brass ContributorOK. Thanks Paul. I'll put in a support call to MS.