Forum Discussion

azeem1670's avatar
azeem1670
Copper Contributor
Sep 01, 2024
Solved

Actual start date vs Start date

Please guide, How can we keep actual start date and actual finish date different from start date and finish date?
  • malshayeb's avatar
    Sep 02, 2024
    the way MS project work is once you have set an actual start or finish it will also set the start and finish to reflect a realistic planning, if you want to preserve the dates you have to set a baseline and with that baseline when you set actuals you get variances and it open up the door to more cool information about your project πŸ™‚ hope that helps