Railway construction km Filter
- Jul 24, 2023
This is what I get when I create a filter based on the Date Range filter. Does it not do what you want?
John
I have crated the same Filter, and when I apply it to the range of KM 6 and KM7 than only Task 2 appears.
But what I need is that all 4 activities needs to appear, because they have workload in this km range.
Do you have any Idea?
Hello ThomasvP
The filter that John describes works correctly
You can add it to ask the interval of kilometers as indicated in the attached video.
Regards
- ThomasvPJul 25, 2023Copper Contributor
Hey both, thanks so much. now it is working.
(I mixed up start and finish before)
- John-projectJul 25, 2023Silver Contributor
Yeah, I thought maybe that was the problem. I'm glad you got it working and thanks for the feedback.
If I answered your question, please consider marking my response as the answer.
John