Forum Discussion
Railway construction km Filter
- Jul 24, 2023
This is what I get when I create a filter based on the Date Range filter. Does it not do what you want?
John
Take a look at the Date Range filter and modify the fields as appropriate for your needs.
John
Hi John,
thanks for the support. I changed the Date Range filter accordingly but,
when I sete the range filter from 6km Start to 7km End, will not schow the activities witch goes e.g. Start 5km to 10km.
How can I set a Filter witch includes these tasks also?
Many Thanks in advance,
Thomas
- John-projectJul 24, 2023Silver Contributor
This is what I get when I create a filter based on the Date Range filter. Does it not do what you want?
John
- ThomasvPJul 24, 2023Copper Contributor
I have crated the same Filter, and when I apply it to the range of KM 6 and KM7 than only Task 2 appears.
But what I need is that all 4 activities needs to appear, because they have workload in this km range.
Do you have any Idea?
- Ignacio_MartinJul 25, 2023Steel Contributor
Hello ThomasvP
The filter that John describes works correctly
You can add it to ask the interval of kilometers as indicated in the attached video.
Regards