Forum Discussion
Monty Evans
Apr 19, 2024Tin Contributor
Question on difference PWA instances
Hi, I am researching how to setup permissions in PWA. I'm a SharePoint Administrator, so I understand those permissions and I see there is a way to change the permission management between ShareP...
- Apr 20, 2024Monty --
To give you the control you want with Project Web App, I definitely agree you need to change the default setting to Project Permissions Mode. This will allow you to control permissions through the use of Groups and Categories.
Also, to ease your mind, the setting you will be changing will only affect YOUR OWN Project Web App instance, and will not impact any others in your organization. Hope this helps.
Apr 20, 2024
Monty --
To give you the control you want with Project Web App, I definitely agree you need to change the default setting to Project Permissions Mode. This will allow you to control permissions through the use of Groups and Categories.
Also, to ease your mind, the setting you will be changing will only affect YOUR OWN Project Web App instance, and will not impact any others in your organization. Hope this helps.
To give you the control you want with Project Web App, I definitely agree you need to change the default setting to Project Permissions Mode. This will allow you to control permissions through the use of Groups and Categories.
Also, to ease your mind, the setting you will be changing will only affect YOUR OWN Project Web App instance, and will not impact any others in your organization. Hope this helps.
- Monty EvansApr 22, 2024Tin ContributorDale,
Yes, this helps a lot!
Thanks for the reply!
-Monty