Forum Discussion
Jerome_Teoh
Dec 20, 2022Copper Contributor
Question marks in the duration?
Hi, I am wondering why I always have question mark on the duration? Thanks, Jerome.
TonyProctor
Dec 20, 2022Copper Contributor
Jerome_Teoh great question. If you double click the task, go to the "Advanced" tab and uncheck the "Estimated" checkbox then it will go away.
**Tip: If you go to the "File" tab, Options (at the bottom), click the "Schedule" link on the left and then uncheck the "Show that scheduled tasks have estimated durations". This will remove it in the ENTIRE schedule ; )
Let me know if that resolves it for you.