Forum Discussion
Question about enhancing the appearance of a roadmap in MS Project Online
Dale_HowardMVP, thank you again for your follow up! I am not an administrator in our version of Microsoft Online and don't have access to PWA. So I sent an email to the person who is our administrator and requested that he set up the Timeline view at the top of the Project Center page in PWA for me. That probably won't happen until tomorrow. I did look at YouTube videos of using timelines and it certainly has more features to improve the display of the timeline. But the video is showing a full blown version of MS Project. The version of MS Project online I have seen clearly does not have this timeline feature, so I am interested to see how this will work out once I get access to the Timeline view with MS Online.
Michael
The Timeline view in Project Web App has most of the features of the Timeline view found in the Microsoft Project desktop application. However, I doubt anyone has done a YouTube video on using the Timeline view in PWA. Your Project Online application administrator should be able to create a Timeline view at the top of the Project Center page that will meet your specifications. He/she needs to add you to the Project Managers security group in PWA so that you can access the system.
Project Web App, by the way, is the web-based user interface to Project Online. Hope this helps.
- meperlmanMar 15, 2022Tin ContributorDale,
Thanks for the additional detail! I am still trying to get access to PWA. I will let you know when I can get there and look around.
Michael- Mar 15, 2022
meperlman - It just dawned on me that even though you said you are using Project Online, you might actually be using Project for the Web. When you created your projects, did you use a web-based user interface that looks something like this?
If yes, you are using Project for the Web and NOT Project Online. And in that case, you can disregard my comments about Project Web App and the Timeline view in the Project Center page. The answer to your question is that you cannot apply much in the way of formatting to the Roadmap application. Hope this helps.
- meperlmanMar 15, 2022Tin ContributorDale, you are correct, I was using Project for the Web and the project does look like the image you show. So, I should use Project Online instead? How do you get access to Project Online so that I can create the MS project there? If I have access to PWA will that give me access to Project Online?
Michael