Forum Discussion
PWA-SharePoint - Access Rights / Settings
Hello tayram,
To clarify, when you say the Owner added the user to the Project Team in this the Microsoft Team for that project or are you referring to the project owner using the build team feature in Project Online? Either way, you will need to ensure that user is added to the Project Site if they need access to the Project site document library. Project Online can handle this access / permission sync if you are using the "Project permission" which you state you are and providing the Project Sites are in the PWA site collection. You would just need to ensure that on the Enterprise Project Types (EPT) settings you have "Sync User Permissions" enabled. Project Online will then use the PWA access model to determine which users to sync to which project sites.
Paul