PWA Permission Management
Hello,
why can I see Projects in PWA from Groups, that I'm not even a member of?
How can we change that in our settings?
Regards
1 Reply
- Timo --
Your question is impossible to answer in this public user forum because we cannot actually see and examine your Project Online or Project Server system. The permissions given in PWA are based on both the security Groups to which a user belongs AND the security Categories that are included in each security Group. Assuming you are the application administrator of your PWA, navigate to the Manage Users page, select your name, and then click the Check Effective Rights button. The resulting page should tell you the rights and permissions you have and from which Groups and Categories those rights and permissions are based. That's probably the best we can do for you. Sorry, but hope this little bit helps.