PWA Notes field is disabled

Hello,

 

I added the Notes field to the Task Summary view but I am unable to edit the Notes, it is disabled or read only. Is there something I need to do to enable it?

 

thank you

  • Hello tonytohme ,

    The Notes field is not editable in the PWA task grid, it is read-only there as you have seen. I guess this is due to the field supporting rich text.

    Paul

6 Replies

  • Hello tonytohme ,

    The Notes field for Tasks is editable in the Project Desktop client. You can either add notes in the Task Information:

     

    Or in the view:

     

    I hope that helps

    Paul

    • tonytohme's avatar
      tonytohme
      Copper Contributor

      Paul_Mather 

      Thanks for your help, but I am using PWA (Project Online), and the Notes field is in the summary task but I cannot edit it for some reason.

       

      • Paul_Mather's avatar
        Paul_Mather
        MVP

        Hello tonytohme ,

        This field is editable in the desktop client. The assigned users can also add notes from the Task page in PWA:

        Paul