PWA Auto Publshing after tasks approval
- Nov 04, 2022
Hello Peter_ayad ,
For these changes to be visible in PWA and the Reporting data set, the projects need to be published. You can do the approval and publish all from PWA:
- Access the Approvals page, the Status Manager for the tasks will see the task approvals here.
- Approve the Task Update/s
- Remaining on the Approvals page, click the History button and click Status Updates on the ribbon
- Select the Task Update/s and then click the Publish button on the Status Update ribbon:
That might be a bit more efficient if you are doing the manual approvals if you are not doing it that way already.
You could also look to set up a rule for auto approval and set that to publish the updates:
You will see this on the Approvals page:
Hope that helps
Paul
- Access the Approvals page, the Status Manager for the tasks will see the task approvals here.
Hello Peter_ayad ,
For these changes to be visible in PWA and the Reporting data set, the projects need to be published. You can do the approval and publish all from PWA:
- Access the Approvals page, the Status Manager for the tasks will see the task approvals here.
- Approve the Task Update/s
- Remaining on the Approvals page, click the History button and click Status Updates on the ribbon
- Select the Task Update/s and then click the Publish button on the Status Update ribbon:
That might be a bit more efficient if you are doing the manual approvals if you are not doing it that way already.
You could also look to set up a rule for auto approval and set that to publish the updates:
You will see this on the Approvals page:
Hope that helps
Paul
- Peter_ayadNov 07, 2022Copper ContributorMany thanks, Paul, for your reply!
I will definitely try it and let you know how it goes.