PWA - Timesheet that is not approved not showing in Approvals

I have a staff member whose timesheet from December 2024 is not approved, but it's not showing anywhere in Approvals or history for me to approve. The timesheet contains only Administrative time. How can I approve this timesheet?

What he sees: 

I see nothing in approvals, or in History for that period. 

1 Reply

  • Andyman --

    Have you been able to approve timesheets previously for this user?  Or have you ONLY been approving task updates (task progress) for this user?

    If your organization wants to you to be able to approve timesheets, such as the situation you describe where the timesheet only includes Administrative time, your Project Online application administrator needs to include you in the default Resource Managers group in PWA.  Has that been done already?  If not, please ask your app admin to do this and then let us know if that solves the problem.  Thanks!