Forum Discussion
BlissL
Aug 22, 2022Brass Contributor
Pull through enterprise lookup table into Project Professional custom field
Hi there, I have a Project 3 license and I have a custom text task field called "Accountable" where I want to add resources who should be Accountable for the task (in line with the RASCI model -...
- Aug 23, 2022BlissL --
Good. But did you remember to make this field a multi-value field? If not, you will have to delete the field and recreate it. Does that help? Please let us know and we will try to help you.
Aug 23, 2022
BlissL --
The custom task field needs to be a custom enterprise task field. When you create it as a custom enterprise field, you can attach the lookup table containing your list of generic resources, and you can designate it as a multi-value field as well. Hope this helps.
The custom task field needs to be a custom enterprise task field. When you create it as a custom enterprise field, you can attach the lookup table containing your list of generic resources, and you can designate it as a multi-value field as well. Hope this helps.
- BlissLAug 23, 2022Brass Contributor
Hi Dale_HowardMVP,
I think from my end I have set up the custom enterprise field as a task field, and assigned the correct lookup table (that I created) for the custom field -
- Aug 23, 2022BlissL --
Good. But did you remember to make this field a multi-value field? If not, you will have to delete the field and recreate it. Does that help? Please let us know and we will try to help you.- BlissLAug 23, 2022Brass Contributor