Forum Discussion

tanzimshaikh's avatar
tanzimshaikh
Brass Contributor
Mar 27, 2024
Solved

Publishing updates in Sub Projects does not reflect it in the Master Project through EPM PWA

Hello, We have couple of projects under a Master project in Project Server 2019 (on-premises). However when we update the sub-projects, the updates does not reflect in the Master Project.   Than y...
  • Dale_HowardMVP's avatar
    Dale_HowardMVP
    Apr 03, 2024
    Tanzimshaikh --

    Thanks for the response. Even though your PMs have updated their projects using the PWA user interface, they will still need to open their projects in Microsoft Project and then publish the latest changes. This will cause the master project to be updated. Hope this helps.