Forum Discussion

David_Smith756's avatar
David_Smith756
Copper Contributor
Apr 12, 2024
Solved

Projects Online Desktop Client Sync with PWA Issue

I've created a custom field in Projects Online Desktop Client labeled Used Budget. I then went into PWA and created the same custom field and labeled it as such. I've been trying to sync the data fro...
  • RodFromm's avatar
    Apr 12, 2024

    David_Smith756 You created two separate fields with the same name. The one created in Desktop is unique to that project, while the one created in the PWA can be included in any project in your PWA. 
    To transfer the value over to the PWA custom field, go to the PWA, open the project in MSP Desktop, add both fields to your view and manually transfer the values. If it no longer needed, you can delete the field you created in desktop.  You'll have to repeat this in each project.