Forum Discussion
Projects Online Desktop Client Sync with PWA Issue
- Apr 12, 2024
David_Smith756 You created two separate fields with the same name. The one created in Desktop is unique to that project, while the one created in the PWA can be included in any project in your PWA.
To transfer the value over to the PWA custom field, go to the PWA, open the project in MSP Desktop, add both fields to your view and manually transfer the values. If it no longer needed, you can delete the field you created in desktop. You'll have to repeat this in each project.
David_Smith756 You created two separate fields with the same name. The one created in Desktop is unique to that project, while the one created in the PWA can be included in any project in your PWA.
To transfer the value over to the PWA custom field, go to the PWA, open the project in MSP Desktop, add both fields to your view and manually transfer the values. If it no longer needed, you can delete the field you created in desktop. You'll have to repeat this in each project.
- David_Smith756Apr 16, 2024Copper ContributorSo if I'm understanding what you're saying, I would have to manually take the value from the Desktop project then manually enter it into the PWA of the same Project. If that's the case is there a way to automat it so when I enter a value in that desktop custom field that it would pass through to PWA?
- RodFrommApr 16, 2024Iron Contributor
David_Smith756 - Once you create the field in the PWA, you open the project from the PWA in Desktop and you can add the custom field to your view and update it. There is no need to transfer the value.
- David_Smith756Apr 16, 2024Copper ContributorPerfect! Thank you.