Forum Discussion
BlissL
May 18, 2022Brass Contributor
Projects not showing in PWA Project Center
Hi again, I'm on a Project Professional 3 license with (what looks like) admin access on the PWA sharepoint site, yet none of my projects are showing in the Project Center. I can see ...
BlissL
May 19, 2022Brass Contributor
When I click on a PWA Project in the recent list from Project Home, this is what comes up:
Only after clicking edit does the detail come up - is this to be expected?
And then after saving the CHEMICAL DEVELOPMENT project, it came up on the PWA Project Site, but the SCOPING project seemed to require publishing before it showed up - is this normal as well?
Paul_Mather
May 20, 2022MVP
Hello BlissL ,
That is expected behaviour, projects need to be published to see the projects / latest changes in PWA. If you publish the Projects in PWA you will then see these in the Project Center views.
Paul