Project Web App (Project Online) Connectivity to Power BI through OData
I am trying to connect my Project plan which is in Project online (PWA) to Power BI through OData for custom PBI reporting of Project plan. I can get all the table's for PBI Visualisation. I am u...
Karl STEWING
May 10, 2018Copper Contributor
The link chain is the following:
TaskId (Tasks) <-> TaskId (Assignments)
ResourceId (Resources) <-> ResourceId (Assignments)
Do you have both?
Madan kumar
May 10, 2018Copper Contributor
Hi Karl,
Yes the relationship is established , I have attached the screenshot.Please refer the same
- Ian BrucknerMay 11, 2018Iron Contributor
I'm having trouble envisioning what your actual problem is then. Can you share more about the filter or what the report looks like?