Project Web App (Project Online) Connectivity to Power BI through OData
Hi Karl,
Thanks for your reply, I did tried i can now bring in the resources through Assignment table but i am unable to see the user specific tasks on my report.
There is a relationship between two table Assignment table and Task Table (Unique Value is Task Id)
E.g. Task 1 is assigned to User A, Task 2 to User B and Task 3 to User C, When the select User A it still shows me all the tasks. I have to see Task 1 as per my filter selection.
Have you linked assignments to resources on ResourceId yet?
- Madan kumarMay 10, 2018Copper Contributor
Yes I Did, There is a relationship between the two tables
- Karl STEWINGMay 10, 2018Copper Contributor
The link chain is the following:
TaskId (Tasks) <-> TaskId (Assignments)
ResourceId (Resources) <-> ResourceId (Assignments)
Do you have both?
- Madan kumarMay 10, 2018Copper Contributor
Hi Karl,
Yes the relationship is established , I have attached the screenshot.Please refer the same